Buying land and building on it
A plot is real estate: the steps above apply, with 3% transfer tax and, for buyers from outside the EU, EEA and Switzerland, the Ministry of Defence permit. What you may build is decided by the land use plan and a building permit, so check both before you buy.
What the plan allows
- Local detailed plan (asemakaava): sets where buildings go, how big they are and what they are for. Building rights (rakennusoikeus) are given as floor area in m². Finnish environment administration
- Local master plan (yleiskaava): a general plan, which can be detailed enough to guide building directly, especially on shores and in villages.
- Shore plan (ranta-asemakaava): a plan for building on shores, mainly holiday homes.
Kittilä (Levi) publishes its plans and building guidelines online. Kittilä plans
Land outside a detailed plan
By law a building site there must be at least 1,000 m², with buildings at least 4 m from the boundary, road access, and water and wastewater handled without harm; the building permit checks this. Kittilä asks for more: a residential site of at least 3,000 m² (2,000 m² if it joins the sewer). A property without a main building in an unplanned area usually has no building site, and so no building rights. Kittilä building ordinance 2026 Building Act
By the water
Without a detailed plan or a master plan made to guide building, you may not build on a shore. You first apply to the municipality for an exception decision, then for the building permit; if you buy unplanned land, a preliminary contract first is wise. In Kittilä, buildings needing a permit stand at least 30 m from the shoreline, with at most one holiday or residential building (up to two homes) and 250 m² of floor area on a shore site. shore plans exceptions
Buying part of a property
If you buy an area cut from a larger property (määräala), the National Land Survey forms it into a property of its own. Your title application starts this; it takes about six months, and the fee depends on the area (the seller pays unless agreed otherwise). National Land Survey
The building permit
- Needed for any home, and for any building of 30 m² or 120 m³ or more. Building Act
- In Kittilä you apply online through Lupapiste, with drawings by a qualified designer. The work needs a head designer and a responsible site manager (vastaava työnjohtaja). Kittilä building control Lupapiste
- Building must start within three years and be finished within five; both can be extended.
- The building can’t be used until building control approves it at the final inspection.
- Kittilä’s fee: €450 per building plus €5.80 per m² of floor area (€950 plus €5.80 per m² outside planned areas). Kittilä fees
Water, power and roads
Away from the municipal network you need your own water and a wastewater system that meets the treatment rules; ask the water utility early whether you can connect. The local electricity network company connects new sites on request and gives a cost estimate. A private road is maintained by its users together, each paying a share. Ministry of the Environment
Municipal plots in Levi
Kittilä sells building plots in Levi, including holiday plots, with applications open at set times. Ask about the terms, such as any deadline for building, before you apply. Kittilä plots for sale